Key Dates
02 December → 15 December 2019
Exhibition Period for Dianella Street Reserve Playground Replacement consultation
07 December 2019
Drop-in Information Session – 11am to 12pm
7 December 2019
Location. Dianella Street Reserve
Location. Dianella Street Reserve
03 December 2019
Drop-in Information Session – 3pm to 5pm
3 December 2019
Location. Dianella Street Reserve
Location. Dianella Street Reserve
April → June 2020
Stage 1 - Playground upgrade - PROPOSED WORKS
April to June 2020, using available 19/20 Capital Works funds.
Works include removal of existing playground and construction of new playground in centre of reserve, with footpath and landscape improvements (refer to ‘Dianella Street Reserve & Carpark’ plan).
Works include removal of existing playground and construction of new playground in centre of reserve, with footpath and landscape improvements (refer to ‘Dianella Street Reserve & Carpark’ plan).
July → December 2020
Stage 2 - Sports field upgrade - PROPOSED WORKS
July to December 2020, using proposed 20/21 Sports field Renewal Program funds.
Works include regrading and returfing to improve playing surface for soccer & cricket games, including drainage improvement (refer to ‘North Caringbah Oval plan’).
Works include regrading and returfing to improve playing surface for soccer & cricket games, including drainage improvement (refer to ‘North Caringbah Oval plan’).
October → December 2020
Stage 3 - Car park upgrade- PROPOSED WORKS
October to December 2020, using proposed 20/21 Car Park Renewals Program funds.
Works include additional six parking spaces, resurfacing car park and improvement of pedestrian access and connection points (refer to ‘Dianella Street Reserve & Carpark’ plan).
Works include additional six parking spaces, resurfacing car park and improvement of pedestrian access and connection points (refer to ‘Dianella Street Reserve & Carpark’ plan).